  1. 01

    Collection & Sorting

    We collect agricultural waste vinyl, cut it and pick out other materials and foreign matter.

  2. 02

    Shredding & Washing

    After shredding to a set size, a 1st and 2nd wash removes soil and residue.

  3. 03

    Dewatering

    A 1st and 2nd dewatering lowers the moisture of the material before extrusion.

3-stage extrusion · 3-stage filtration

Stage 1·2·3 extrusion and 3-stage 80~120 mesh filtration make uniform, clean molten resin.

Production Process Chart

Multi-stage filtration system - removal of foreign matter in recycled material - physical process - optimized production process and power use (cost) - use of solar renewable energy

  1. 01Collection & Sorting
  2. 02Shredding & Washing
  3. 03Dewatering & Drying
  4. 04Melting, Extrusion & Filtration
  5. 05Cooling & Cutting
  6. 06Quality Inspection & Storage

Process Details

From collection to storage, see the equipment, control indicators and quality checks of each of the six process steps.

  1. Step 01

    Collection & Sorting

    Collected agricultural waste vinyl and waste plastics are cut, and other materials and impurities are separated on the sorting table. Sorting precision here decides the quality of every later process.

    Input Material
    Farm waste vinyl PCR
    Sorting Method
    Machine sorting, visual sorting
    Removed
    Soil, string, labels, foreign resins
    Main Equipment
    Sorting conveyor, hand-sorting table
  2. Step 02

    Shredding & Washing

    Sorted waste vinyl is shredded to a set size, then multi-stage washing removes the soil and organic matter on its surface. The washing level at this step decides the color and odor of the final pellets.

    Shredding Method
    Wet shredder
    Washing Process
    Multi-stage water and friction washing
    Wash Water
    Reused after purification and filtering
    Main Equipment
    Shredder, washing screw
  3. Step 03

    Dewatering & Drying

    Centrifugal dewatering removes the water from the washed flakes and hot-air drying lowers their moisture content. Moisture left behind causes bubbles and weaker properties at extrusion, so this is the hardest section to control.

    Dewatering Method
    Centrifugal dewatering
    Drying Method
    Hot-air drying
    Control Indicator
    Moisture content
    Main Equipment
    Shredder, washing screw
  4. Step 04

    Melting, Extrusion & Filtration

    The dried flakes are melted and extruded, and fine foreign matter is filtered out in the molten state. Dongmin applies 2-stage extrusion and 2-stage filtration to remove impurities step by step.

    Extrusion Setup
    2-stage extrusion (Primary · Secondary)
    Filtration Setup
    2-stage filtration
    Control Indicator
    Melt temperature · discharge pressure
    Main Equipment
    Extruder · filter screen
  5. Step 05

    Cooling & Cutting

    The extruded strands are cooled in water and cut to a set length to form pellets. The cutting conditions set the particle size, and an even particle size keeps feeding stable in customers' equipment.

    Shredding Method
    Wet shredder
    Cutting Method
    Strand cutting
    Control Indicator
    Particle size · length variation
    Main Equipment
    Cooling bath · cutter
  6. Step 06

    Quality Inspection & Storage

    Finished pellets are tested by grade, and only lots that meet the specification are shipped. Test results are compiled into a TDS and test reports and supplied with each delivery.

    Test Items
    Density · tensile strength · elongation
    Visual Inspection
    Color · foreign matter · particle size
    Control Indicator
    Ton bags · kraft sacks
    Storage
    Stored separately by grade

Site Photos

Our production floor, photographed at our Yeongcheon site.